by WebDoc | Jan 20, 2020 | Fisher Tools
The shell project is complete. Landscaping and paving are done and the owner has commenced the interior build.
by WebDoc | Oct 15, 2019 | Fisher Tools
The roof plywood decking is complete. Next we need to add foam on top of the decking for insulation. That’s it for this week’s update. Come back next time and we’ll see the foam completed and possibly even the elastometric coating. In the meantime, if you’d like more...
by WebDoc | Aug 25, 2019 | Fisher Tools
The columns are complete and trusses are are being installed this week. Crews are about 85% complete. That’s it for this week’s update. Come back next time and we’ll check out what roofing material will be used to seal the building. In the meantime, if you’d like more...
by WebDoc | Jul 20, 2019 | Fisher Tools
This week the masons are getting close to the top of the exterior structural wall. That’s it for this week’s update. Come back next week and…. [insert lead into next post]. In the meantime, if you’d like more information about warehouse building or have questions on...
by WebDoc | Jun 22, 2019 | Fisher Tools
This week the masons are cruising right along with the exterior masonry wall. That’s it for this week’s update. Come back next week and…. [insert lead into next post]. In the meantime, if you’d like more information about warehouse building or have questions on how to...
by WebDoc | Jun 15, 2019 | Fisher Tools
This week the foundation is placed and is curing. The masons have set up jack scaffolds in one corner and they have stocked materials around the perimeter of the foundation in preparation to start the structural exterior walls. Did you know it takes concrete 28 days...