Fisher Tools Progress Update – Week 9

The foundation prep work is just about complete and the underground utilities are being installed. It is crucial at this stage to check and double check all the conduits, piping, sleeves and penetrations are where they need to be. Once the foundation is placed we...

Fisher Tools Progress Update – Week 8

This week we are preparing the soil for the foundation. Engineering specifications require a minimum compaction for soil before a foundation is placed which is usually 98% compaction. This helps prevent the building from settling unevenly which can cause serious...