Biogas Project

  • Date: 12 April 2018
  • Client: Arizona Public Service (APS)
  • Project Type: Underground

About this Project

A 3 week, 1/2 mile underground project at 2 Dairies using methane generators to produce power to supply back to APS grid.

  • Construct Utility Vaults
  • 54,000 feet Conduit Installation
  • Cranes
  • 4 Excavators
  • 1 Caterpillar Dozer
  • Traffic Control and Terminations